FORTHCOMING ROADWORKS as notified to us *****UPDATED*****
Please note that the block pave sections near the village corner and on Waldron Road will be replaced once the roadworks has been completed. The pavers are begin securely stored and any broken ones are being sourced for replacement. The black tarmac in these sections is TEMPORARY.
16th September to 18th October
Waldron Road (leaving village), Traffic Lights, Electricity work.
9th October to 13th November (may be extended)
Graywood Road, Road Closed, Electricity work (diversion in place)
2nd to 24th October
London Road, Traffic Lights, South East Water
13th November to 6th December
High Street, Traffic Lights, Electricity Work
6th December to 20th December
South Street, Traffic lights, Electricity Work
Correct as at 4th October 2024