FORTHCOMING ROADWORKS as notified to us *****UPDATED*****

Redrow Liaison Group Uploaded on October 7, 2024

FORTHCOMING ROADWORKS as notified to us *****UPDATED*****

 

Please note that the block pave sections near the village corner and on Waldron Road will be replaced once the roadworks has been completed. The pavers are begin securely stored and any broken ones are being sourced for replacement. The black tarmac in these sections is TEMPORARY.

 

16th September to 18th October

Waldron Road (leaving village), Traffic Lights, Electricity work.

 

9th October to 13th November (may be extended)

Graywood Road, Road Closed, Electricity work (diversion in place)

 

2nd to 24th October

London Road, Traffic Lights, South East Water

 

13th November to 6th December

High Street, Traffic Lights, Electricity Work

 

6th December to 20th December

South Street, Traffic lights, Electricity Work

 

Correct as at 4th October 2024